Companies approuved for the Benin Free Processing Zone until now: AFOKANTAN BENIN CASHEW SA (29-09-05); POWER ON MANUFACTURE SA (02-03-06) ; CRUSTAMER SARL (28-04-06) ; ALPHA BENIN SA (30-06-06) ; SHUNFENG SA (25-07-07) ; JUPITER IMPEX Sarl (12-09-07) ; YULIN Sarl (14-02-08) ; AFRICA FOOD PROCESS Sarl(14-02-07) ; REDDY INVESTMENTS Sarl (14-02-08)
>>> <<<
 
 
Procedures
 
 
Download the kit of the files here required for the application. As of approval, confirm engagement while proceeding to the study on the environmental impact of your project. Recover here the list of the notarial cabinets entitled to accompany you during this stage and the formalities at the CFE/CCIB for creation of a company.
 
 

Steps

Structure

Deadline

Fees

01

Withdrawal of the standard document of admission requirement under the scheme of the Free Processing Zone (FPZ)

A-ZFI

---

---

02

Submission of the admission application file under the IFPZ scheme in three (03) copies of which one (01) original and two (02) photocopies

A-ZFI

---

0,2% of the investment upraised at CFA 5,000,000

03

Delivering of a file conformity receipt

Secretary of the Admission Commission

Fifteen (15) days

---

04

Meeting of the Admission Commission to FPZ scheme

Secretary of the Admission Commission

Seven (07) days

---

05

Decision of the Admission Commission under the IFPZ scheme

Secretary of the Admission Commission

Thirty (30) days for enterprises and forty five  (45) for zone promoters from the day of the delivering of file conformity receipt

---

06

Transmission to the investor the inter-ministerial order of admission under the FPZ scheme

Secretary of the Admission Commission

---

---

07

Control of  the conformity of the setting up site

A-ZFI

Seven (07) days after the transmission of the order of admission

---

08

Presentation of the fabric plan of building

A-ZFI

Before the beginning of the works

---

09

Beginning of the development, building and fitting step

Investor

Maximum of six (06) months after of the order of admission

---

10

Period of development, building and fitting before exploitation

Investor

Thirty (30) months  after the order of admission

---

11

Report on the state of evolution of the works

Investor

Every three (03)  months

---

12

Delivering of a conformity certificate at the end of the works

A-ZFI

Fifteen (15) days after the end of the works

---

13

Payment of the annual licence fees

Investor

1.500.000 F CFA

14

Beginning of exploitation

Investor

Thirty (30) months  maximum after the order of admission

Presentation of the files to be submitted to FPZB to be downloaded in word or PDF.
 